top of page

Instruct Newsletter #20 - NEC - Selecting X Clauses: Are you getting it wrong?

19/08/24

This article is brought to you by Instruct, a knowledge hub centred around NEC, distributing a weekly newsletter and have an in-house AI knowledge system tailored to NEC4 contracts and specifically NEC4 ECC. Check out their website and LinkedIn page for more information, keep updated, and subscribe to their Newsletter or AI knowledge system.

Instruct Newsletter #20 - NEC - Selecting X Clauses: Are you getting it wrong?


Welcome to the Instruct newsletter. Bringing you weekly NEC knowledge, like the postman, but we only bring good news!



Developing your contract can be time consuming, drafting the Scope, collating Site Information, picking the team, and selecting X Clauses!

Are you getting it wrong!?

This week we assess:

  1. What is an X Clause?

  2. How to select the ones you want?

  3. How getting it wrong can impact your project!

Let’s begin…


1. What is an X Clause?


NEC contract are compiled of Core, Main Option, and Secondary Option Clauses.

Within Secondary Option Clauses you have X, Y, and Z


X - Secondary Option Clauses (X1-X22 for NEC4 ECC)


Y - Y(UK)1 Project Bank Account, Y(UK)2 The housing Grants, Construction and Regeneration Act 1996, The Contracts (Rights of Third Parties) Act 1999


Z - Additional Conditions of Contract


X Clauses


There are 22 X clauses in the NEC4 ECC contract, they are:


  • X1: Price Adjustment for Inflation

  • X2: Changes in the Law

  • X3: Multiple Currencies

  • X4: Ultimate Holding Company Guarantee

  • X5: Sectional Completion

  • X6: Bonus for Early Completion

  • X7: Delay Damages

  • X8: Undertakings to the Client or Others

  • X9: Transfer of Rights

  • X10: Information Modelling

  • X11: Termination by the Client

  • X12: Multiparty Collaboration

  • X13: Performance Bond

  • X14: Advanced Payment to the Contractor

  • X15: The Contractor’s Design

  • X16: Retention

  • X17: Low Performance Damages

  • X18: Limitation of Liability

  • X20: Key Performance Indicators

  • X21: Whole Life Costing

  • X22: Early Contractor Involvement


Think of the X clauses as a shopping list, a means of incentivising, penalising, and mandating your requirements to the Contractor. It also establishes protocol for the Client, e.g. X1 requiring the Client to take the risk of inflation!


You can tell which X clauses have been included as they are shown in Contract Data part 1!


2. How to select the ones you want?


Selecting X clauses is both simple and complicated. We’ll give some examples below, but first you should do this when setting up a contract:


  1. Read each X clause and understand its intention (e.g. X7 Delay Damages. The Contractor pays a set amount if they are late!)

  2. Write down the key objectives of the contract/ project (time, cost, quality). What are you trying to achieve and what is most important? e.g. cheap as possible or fast as possible?

  3. Work through each X clause and decide whether it will help you to achieve your objectives.


Bear in mind…depending on market conditions, some Contractor may not be willing to enter into difficult contracts. Make your contract as appealing as possible whilst still protecting your objectives!


Example!

You need to build a new motorway with the following criteria:

  • Client is building the project for someone else

  • Inflation is uncertain

  • Fixed budget, but there is some additional funds kept in reserve

  • 1 Year programme, can’t be late!

  • Contractor is to design & build


Here’s what we would select and why:


  • X1: Price Adjustment for Inflation - Because inflation is uncertain and Contractor’s wont sign without it!

  • X6: Bonus for Early Completion - Opening the motorway earlier is a big win for the Client, and it can’t be late! Positive for the Contractor.

  • X7: Delay Damages - To compensate an early bonus, there is also a penalty for being late! The Client could need this money to keep the project in budget.

  • X8: Undertakings to the Client or Others - The project is for someone else (not the Client), so we need an undertaking

  • X9: Transfer of Rights - The Client wants full ownership of the design

  • X10: Information Modelling - Could be used but we haven’t stipulated it here!

  • X11: Termination by the Client - Client needs to terminate for any reason!

  • X14: Advanced Payment to the Contractor - The Client is willing to cashflow the Contractor in the early days. This boosts Contractor engagement.

  • X15: The Contractor’s Design - The Client wants clear liability for the Contractor’s design, at a ‘reasonable skill and care’ level.

  • X16: Retention - To balance an advanced payment, the Client will utilise retention


Now this is a short summary and reason why, but look closely, what does this selection of X clauses achieve?


  1. Incentive for the Contractor (advanced payment, bonus for early completion, payment adjustments for inflation)

  2. Risk management by Client (Delay damages, transfer of rights, undertakings, termination)

  3. A good balance aimed at project delivery, not unnecessary penalty.


3. How getting it wrong can impact your project!


Getting it wrong can be terrible for relationships and contract performance. Here are some ways in which a bad selection of X clauses can impact your project:


1 All risk, no reward


Client includes for delay damages, termination, and retention.


2 Selected but not Integrated


Some X clauses need requirements to be detailed in the Scope or Contract Data. Fail to do this and the X clause becomes unusable. E.g. X8 requires an undertaking to be in the form set out in the Scope! X15 says the Contractor can use the work it produced for other other, unless stated otherwise in the Scope. You need to ensure the Scope is clear!


3 Incomplete Contract Data


As well as Scope, you need to complete the Contract Data correctly, e.g. X14 Advanced payment is for the amount stated in the Contract Data! X16 Retention can only be used if the figures are correctly inputted into the Contract Data!


Selecting the X clauses is critical in project success, but so is filling out the contract correctly!


How to avoid X clause issues:


  • Read the requirements of each X clause carefully

  • Note where Contract Data or Scope need to reflect the needs of an X clause

  • Compile the relevant Scope and Contract Data, cross checking to ensure clarity

  • Get someone who is trained in NEC contracts to check and verify the contract is complete!


For a full back catalogue of newsletters Click Here

To sponsor our newsletter or be a guest write email us at:


Reading Recommendations

To understand more about how to prepare and manage an NEC contract, the following guidance documents are available.

6 views0 comments

Commentaires

Noté 0 étoile sur 5.
Pas encore de note

Ajouter une note
bottom of page